NCC 2019 Volume One
Search the National Construction Code editions
Part F1 Damp and weatherproofing
Surface water, resulting from a storm having an average recurrence interval of 20 years and which is collected or concentrated by a building or sitework, must be disposed of in a way that avoids the likelihood of damage or nuisance to any other property.
The Objective of this Part is to—
safeguard occupants from illness or injury and protect the building from damage caused by—
surface water; and
external moisture entering a building; and
the accumulation of internal moisture in a building; and
protect other property from damage caused by redirected surface water.
FO1(a) aims to minimise the risk of water leaking into or accumulating within a building and causing musty, damp and unhealthy conditions or damaging building elements by corrosion.
FO1(b) aims to minimise the risk of other property being damaged by surface water redirected from a building or any associated sitework.
Construction on an allotment must not cause re-directed water damage to “other property”, including:
A building including any associated sitework is to be constructed in a way that protects people and other property from the adverse effects of redirected surface water.
Protection from re-directed surface water
People and other property are to be protected from any problems caused by surface water re-directed by a building and any sitework involved in its construction. Remedial works must be undertaken to dispose of any surface water which, because of any variation or addition to its flow caused by any building or sitework, causes harm to people or other property.
A building is to be constructed to provide resistance to moisture penetrating from the outside including rising from the ground.
Resistance to rain, surface water and ground water
A building must resist:
Ground water could enter a building if there are inadequate damp-proof courses or vapour barriers installed, or if other ways of resisting the rising damp have not been provided.
A building is to be constructed to avoid the likelihood of—
the creation of unhealthy or dangerous conditions; and
damage to building elements,
caused by dampness or water overflow from bathrooms, laundries and the like.
Overflow from bathrooms and laundries
The development of unhealthy conditions or damage caused by dampness or overflow from bathrooms, laundries and the like, must be prevented. Such problems may arise from showers and bathrooms being incorrectly sealed, allowing water to leak into other parts of the building.
Surface water from a 1 in 20 year storm collected or concentrated by a building or sitework must be disposed of without damage to other property.
Construction should not cause stormwater problems on other properties, worse than those which existed previously.
As a general rule, undeveloped land tends to absorb rainwater, usually resulting in comparatively slow run-off.
However, a building's hard surfaces, such as roofs and pavements, cause comparatively quick run-off. Consequently, the design of the surfacewater disposal system must make provision for run-off stormwater from hard surfaces collected or concentrated by a building or sitework.
The storm intensity has been limited to a 1 in 20 year storm. This is considered an appropriate limit, fair on the person responsible for the building and siteworks and the person responsible for properties affected by re-directed surface water.
Surface water, resulting from a storm having an average recurrence interval of 100 years must not enter the building.
FP1.2 does not apply to—
Building and siteworks must be arranged so that surface water from a 1 in 100 year storm does not enter a building.
A 1 in 20 year storm has a less intense flow of water than a 1 in 100 year storm, which is what the subject building must be protected from.
It is considered more important to prevent water entering a building than it is to prevent water entering a neighbouring allotment or property.
The limitations contain several exemptions to FP1.2. These are based on the belief that the use and safety levels of the exempted buildings will not be significantly diminished by surface water entering them.
Limitation (a) regarding Class 7 and Class 8 buildings refers only to such buildings which, in a particular case, do not exhibit any need for compliance with FP1.2. Such buildings must be considered on a case-by-case basis. However, it is the responsibility of a building proponent to satisfy the appropriate authority that the exemption should apply.
A drainage system for the disposal of surface water resulting from a storm having an average recurrence interval of—
20 years must—
convey surface water to an appropriate outfall; and
avoid surface water damaging the building; and
100 years must avoid the entry of surface water into a building.
Under FP1.3(a) a drainage system for the disposal of surface water from a 1 in 20 year storm must:
An outfall includes a kerb and channel, a soakage system, and a natural watercourse, with the decision as to what is appropriate being made by the appropriate authority. Damage to the building could be caused by a building's subsidence.
Under FP1.3(b), a drainage system for the disposal of surface water must avoid surface water from a 1 in 100 year storm from entering a building. This provision is intended to prevent surface water causing internal damage to a building, or causing injury or illness to occupants.
The FP1.3(b) prohibition on surface water entering the building:
A roof and external wall (including openings around windows and doors) must prevent the penetration of water that could cause—
unhealthy or dangerous conditions, or loss of amenity for occupants; and
undue dampness or deterioration of building elements.
FP1.4 does not apply to—
Roofs and walls (including windows, doors and other openings in the walls) must prevent water penetration which could cause dangerous conditions, loss of amenity or dampness and deterioration of building elements.
The limitations contain several exemptions to FP1.4. These are based on the belief that the use and safety levels of the exempted buildings will not be significantly diminished by water entering them.
Limitation (a), regarding Class 7 and Class 8 buildings, refers only to such buildings which, in a particular case, do not exhibit any need for compliance with FP1.4. Such buildings must be considered on a case-by-case basis. However, it is the responsibility of a building proponent to satisfy the appropriate authority that the exemption should apply.
Moisture from the ground must be prevented from causing—
undue dampness or deterioration of building elements; and
unhealthy or dangerous conditions, or loss of amenity for occupants.
FP1.5 does not apply to—
Building elements must be protected from deterioration and occupants must be protected from unhealthy or dangerous conditions or a loss of amenity caused by moisture from the ground (causing such problems as rot, rising damp, rust, and so on). In essence, this requires that the materials and components which make up building elements must either be fit for this purpose or made fit by protection.
The following may be acceptable to achieve compliance with FP1.5. They should not be regarded as absolute.
Overflow from a bathroom, laundry facility or the like must be prevented from penetrating to—
another sole-occupancy unit used for sleeping accommodation; and
a public space,
in a storey below in the same building.
Water overflows from bathrooms, laundries and the like must be prevented from penetrating downwards—i.e. to a storey below—to either another sole-occupancy unit used for sleeping accommodation or a public space. Such overflows are potentially unhealthy and structurally damaging, and can be disruptive for neighbours.
To protect the structure of the building and to maintain the amenity of the occupants, water must be prevented from penetrating—
behind fittings and linings; and
into concealed spaces,
of sanitary compartments, bathrooms, laundries and the like.
The structure of a building and the amenity of its occupants must be protected by preventing water from penetrating behind fittings and linings and into concealed spaces of toilets, bathrooms, laundries and the like.
Compliance with FP1.4 for weatherproofing of an external wall that—
has a risk score of 20 or less, when the sum of all risk factor scores are determined in accordance with Table FV1.1; and
is not subjected to an ultimate limit state wind pressure of more than 2.5 kPa; and
includes only windows that comply with AS 2047,
is verified when a prototype passes the procedure described below:
The test specimen is in accordance with the requirements of (b).
The test procedure is in accordance with the requirements of (c).
The test specimen does not fail the criteria in (d).
The test is recorded in accordance with the requirements of (e).
Risk factor |
Category |
Risk severity |
Score |
Wind region |
Region A (AS/NZS 1170.2) |
Low to medium |
0 |
Region B (AS/NZS 1170.2) |
|||
Region C (AS/NZS 1170.2) |
High |
1 |
|
Region D (AS/NZS 1170.2) |
Very high |
2 |
|
Number of storeys |
One storey |
Low |
0 |
Two storeys in part |
Medium |
1 |
|
Two storeys |
High |
2 |
|
More than two storeys |
Very high |
4 |
|
Roof/wall junctions |
Roof-to-wall junctions fully protected |
Low |
0 |
Roof-to-wall junctions partially exposed |
Medium |
1 |
|
Roof-to-wall junctions fully exposed |
High |
3 |
|
Roof elements finishing within the boundaries formed by the external walls |
Very high |
5 |
|
Eaves width |
More than 600 mm for single storey |
Low |
0 |
451-600 mm for single storey; or |
Medium |
1 |
|
more than 600 mm for two storey |
|||
101-450 mm for single storey; or |
High |
2 |
|
451-600 mm for two storey; or |
|||
more than 600 mm for above two storey |
|||
0-100 mm for single storey; or |
Very high |
5 |
|
0-450 mm for two storey; or |
|||
less than 600 mm for above two storey |
|||
Envelope complexity |
Simple shape with single cladding type |
Low |
0 |
Complex shape with not more than two cladding types |
Medium |
1 |
|
Complex shape with more than two cladding types |
High |
3 |
|
As for high risk but with fully exposed roof-to-wall junctions |
Very high |
6 |
|
Decks, porches and balconies |
None; or |
Low |
0 |
timber slat deck or porch at ground level |
|||
Fully covered in plan view by roof; or |
Medium |
2 |
|
timber slat deck attached at first or second floor level |
|||
Balcony exposed in plan view at first floor level; or |
High |
4 |
|
balcony cantilevered at first floor level |
|||
Balcony exposed in plan view at second floor level or above; or |
Very high |
6 |
|
balcony cantilevered at second floor level or above |
Notes to Table FV1.1 :
Test specimen
The test specimen must incorporate—
representative samples of openings and joints, including—
vertical and horizontal control joints; and
wall junctions; and
windows or doors; and
electrical boxes; and
balcony drainage and parapet flashings; and
footer and header termination systems; and
for a cavity wall—
a transparent material for a proportion of the internal wall lining (to provide an unobstructed view of the external wall cladding) with sufficient structural capability and similar air tightness to resist the applied wind pressures; and
a 15 mm diameter hole in the internal wall lining below a window.
Test procedure
The test procedure for a direct fix cladding wall or unique wall must be as follows:
Apply 100% positive and negative serviceability wind pressures to the external face of the test specimen for a period of not less than 1 minute each.
Apply static pressure of either 300 Pa or 30% serviceability wind pressure, whichever is higher, in accordance with the water penetration test procedure at clause 8.5.2 of AS/NZS 4284.
Apply cyclic pressure in accordance with—
the three stages of Table FV1.2; and
the water penetration test procedure at clause 8.6.2 of AS/NZS 4284.
Stage number | Serviceability wind pressure |
---|---|
1 | 15% to 30% |
2 | 20% to 40% |
3 | 30% to 60% |
The test procedure for a cavity wall must be as follows:
Apply 100% positive and negative serviceability wind pressures to the external face of the test specimen for a period of not less than 1 minute each.
Apply static pressure of either 300 Pa or 30% serviceability wind pressure, whichever is higher, in accordance with the water penetration test procedure at clause 8.5.2 of AS/NZS 4284.
Apply cyclic pressure in accordance with—
stage 3 of Table FV1.2; and
the water penetration test procedure at clause 8.6.2 of AS/NZS 4284.
To simulate the failure of the primary weather-defence or sealing, the following procedure must be applied to the test specimen:
Insert 6 mm diameter holes through the external face of the cavity wall in all places specified below:
Wall/window or wall/door junctions at ¾ height.
Immediately above the head flashing.
Through external sealing of the horizontal and vertical joints.
Within 30 minutes of the completion of (bb), remove the internal lining of the cavity wall and check for compliance with (d).
With the internal lining removed, apply a final static pressure test at 50 Pa for a period of 15 minutes.
Compliance
A direct fix cladding wall and unique wall are verified for compliance with FP1.4 if there is no presence of water on the inside surface of the facade.
A cavity wall is verified for compliance with FP1.4 if there is no presence of water on the removed surface of the cavity, except that during the simulation of the failure of the primary weather-defence or sealing, water may—
transfer to the removed surface of the cavity due to the introduced defects (6 mm holes); and
contact, but not pool on, battens and other cavity surfaces.
Test report
The test report must include the following information:
Name and address of the person supervising the test.
Test report number.
Date of the test.
Cladding manufacturer's name and address.
Construction details of the test specimen, including a description, and drawings and details of the components, showing modifications, if any.
Test sequence with the pressures used in all tests.
For each of the static and cyclic pressure tests, full details of all leakages, including position, extent and timing.
FV1.1 is a means to verify whether or not a proposed external wall achieves the requirements of FP1.4, i.e. whether the wall prevents the penetration of water that could cause:
FV1.1 is not a mandatory component of the NCC, however it is one form of assessment method which can be used to demonstrate compliance with the Performance Requirements.
Other assessment methods in the NCC include:
The Verification Method must be applied in the following order:
This process is shown in Figure FV1.1(1).
Risk factors—Table FV1.1
The risk score is determined by a number of factors including:
The following are examples of typical roof/wall junctions and their associated exposure or protection categories:
Building envelope complexity is determined by the shape and the amount of cladding used. FV1.1 includes both simple and complex shaped buildings:
Test specimen—FV1.1(b)
Representative samples of openings and joints must be included to test the whole cladding system.
This includes samples of:
A test specimen is illustrated in Figure FV1.1(2).
Where a cavity wall is tested, a transparent material must be used in lieu of a portion of the internal wall lining. The transparent material will be used during the testing to observe any water penetration. To ensure an unobstructed view of the external wall occurs, other building components such as building membranes must be removed for the extent of the transparent opening within the internal wall lining. It should be noted that for the purposes of FP1.4 building membranes are not a requirement. However a membrane can be used to achieve compliance with FV1.1.
The transparent material must be installed to maintain similar air tightness as the intended internal wall lining. To simulate the effects of power points, light switches and other similar openings which may cause air leakage, a 15 mm diameter hole must be placed in the internal wall lining below the window.
Test procedure—FV1.1(c)
The test procedure requirements vary in relation to two sub-clauses. FV1.1(c)(i) specifies the test procedure for a direct fix cladding wall or a unique wall. FV1.1(c)(ii) specifies the requirements for cavity wall construction. The difference between the two sub-clauses is FV1.1(c)(ii) has an additional water management test. This is due to cavity wall construction being designed to allow water to pass through the primary weather-defence (e.g. the skin of masonry on a masonry veneer wall), with the function of the cavity allowing for the removal of any water.
Direct fix cladding wall and unique wall—FV1.1(c)(i)
The test procedure for FV1.1(c)(i) contains three steps:
Cavity walls—FV1.1(c)(ii)
The test procedure for FV1.1(c)(ii) contains four steps:
Compliance—FV1.1(d)
Similar to the test procedure, the compliance requirements are separated into two parts and are subject to the type of wall being tested.
FV1.1(d)(i) specifies the compliance requirements for a direct fix cladding wall and a unique wall. Compliance for the testing of these types of walls is met by no presence of water to the inside surface of the facade. This includes the surface of the external wall which is fixed to the internal wall, or for a single skin wall, the internal wall.
The compliance requirements for a cavity wall in FV1.1(d)(ii) are different to the requirements for a direct fix cladding wall or unique wall. This is due to the purpose and nature of a cavity wall. Water which passes through the primary weather-defence will gradually be removed from the cavity either through weep holes or evaporation. FV1.1(d)(ii) therefore allows water to enter the cavity provided water is not present on the removed surface of the cavity. However, there are some exemptions to this, as the water may transfer to the removed surface through an isolated blemish due to the introduced defects. Also, water can contact cavity surfaces such as battens. However, it must be demonstrated that the water will be able to be removed from these surfaces.
The removed surface of the cavity will generally be the outer surface of the internal wall, for example, where the building membrane would be attached to a stud frame.
The purpose of the test report in FV1.1(e) is to record the details and the outcomes of the test. This is common for any test procedure.
FP1.6 is verified when the flow rate of the in-built overflow for all vessels in the room is greater than the flow rate of the source filling the vessel.
FV1.2 only applies to bathrooms, laundries and the like in a Class 2 or 3 building or a Class 4 part of a building.
FV1.2 allows the use of vessels with built-in overflow to provide overflow capacity rather than through the use of a floor waste or other means.