NCC 2019 Volume One
NSW Part J(A)4 Heated water supply

NSW Part J(A)4 Heated water supply

NSW J(A)4.0 Deemed-to-Satisfy Provisions

(a)

Where a Deemed-to-Satisfy Solution is proposed, Performance Requirement NSW J(A)P3 is satisfied by complying with NSW J(A)4.1 and NSW J(A)4.2.

(b)

Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2.2(3) and A2.4(3) as applicable.

NSW J(A)4.1 Application of Part

The Deemed-to-Satisfy Provisions of this Part apply to a Class 2 building and a Class 4 part of a building.

NSW J(A)4.2 Compliance with BCA provisions

Class 2 buildings and Class 4 parts of buildings must comply with the national BCA provisions of J7.2 Heated water supply.

Note: Compliance is not required with the national BCA provisions of J7.3 and J7.4 as those matters are regulated under BASIX.