NCC 2019 Volume One Amendment 1
Search the National Construction Code editions
This Verification Method presents specific design scenarios that must be considered in order to demonstrate that the fire safety aspects of a building design comply with the fire safety Performance Requirements set out in Table 1.1.
The design scenarios specified in Section 2 are summarised in Table 1.1.
Outcome required Note 3 |
Typical method or solution |
||
BE Fire blocks evacuation route (2.1). [A fire blocks an evacuation route] |
CP1, CP2, CP3, CP8, DP4, DP5, DP6, DP7 Note 2, EP1.4, EP2.1, EP2.2, EP4.1, EP4.2, EP4.3 |
Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
Demonstrate that a viable evacuation route (or multiple evacuation route where necessary) has been provided for building occupants. |
UT Fire in a normally unoccupied room threatens occupants of other rooms (2.2). [A fire starts in a normally unoccupied room and can potentially endanger a large number of occupants in another room] |
CP1, CP2, CP3, CP8, DP4, DP5, EP1.4, EP2.1, EP2.2, EP4.1, EP4.2, EP4.3 |
Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
ASET / RSET analysis or provide separating construction or fire suppression complying with a specified Standard. Solutions might include the use of separating elements or fire suppression to confine the fire to the room of origin. |
CS Fire starts in concealed space (2.3). [A fire starts in a concealed space that can facilitate fire spread and potentially endanger a large number of people in a room] |
CP1, CP2, CP3, CP6, CP8, DP4, DP5, DP6, EP1.4, EP2.1, EP2.2, EP4.1, EP4.2, EP4.3 |
Demonstrate that fire spread via concealed spaces will not endanger occupants; and Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
Solutions might include providing separating construction or fire suppression or automatic detection complying with a specified Standard. |
SF Smouldering fire (2.4). [A fire is smouldering in close proximity to a sleeping area] |
CP2, CP3, CP8, DP4, DP5, DP6, EP1.1, EP1.2, EP1.3, EP1.4, EP2.1, EP2.2, EP4.1, EP4.2, EP4.3 |
Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
Solutions might include providing automatic detection and alarm system complying with a recognised Standard. |
HS Horizontal fire spread (2.5). [A fully developed fire in a building exposes the external wall of a neighbouring building] |
CP2 |
Demonstrate that the risk of fire spread between buildings is not greater than buildings complying with the Deemed-to-Satisfy Provisions. |
CV1, CV2. |
VS Vertical fire spread involving cladding or arrangement of openings in walls (2.6). [A fire source exposes a wall and leads to significant vertical fire spread] |
CP2, CP4, CP7, CP8, EP2.2 |
Demonstrate that the building’s external cladding / facade and arrangement of openings in the building do not increase the risk to life resulting from a fire beyond that for a similar building complying with the Deemed-to-Satisfy Provisions. |
CV3. |
IS Fire spread involving internal finishes (2.7). [Interior surfaces are exposed to a growing fire that potentially endangers occupants]. |
CP2, CP4, DP4, DP5, DP6, EP1.1, EP1.4, EP2.1, EP2.2, EP4.1, EP4.2, EP4.3 |
Maintain tenable conditions to allow time for evacuation of occupants and to facilitate fire brigade intervention; and Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
ASET / RSET analysis or equivalent growth and species production rates. |
FI Fire brigade intervention (2.8). [Consider fire brigade intervention] |
CP1, CP2, CP5, CP7, CP9, DP5, EP1.3, EP1.6, EP2.2, EP3.2 |
Demonstrate consideration of potential fire brigade intervention; and Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
Facilitate fire brigade intervention to the degree necessary. |
UF Unexpected Catastrophic Failure (2.9). [A building must not unexpectedly collapse during a fire event] |
CP1, CP2, CP9 |
Demonstrate that the building, its critical elements and the fire safety system provide sufficient robustness such that unexpected catastrophic failure is unlikely; and Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
Undertake review or risk assessment of critical elements within a building to determine unexpected catastrophic failure is unlikely. |
CF Challenging fire (2.10). [Worst credible fire] |
CP1, CP2, CP3, CP8, DP4, DP5, DP6, EP1.1, EP1.2, EP1.3, EP1.4, EP2.1, EP2.2, EP4.1, EP4.2, EP4.3 |
Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
|
RC Robustness check (2.11). [Failure of a critical part of the fire safety systems will not result in the design not meeting the Objectives of the BCA] |
CP1, CP2, CP3, CP8, DP4, DP5, DP7 Note 2, EP1.1, EP1.2, EP1.3, EP1.4, EP2.1, EP2.2, EP4.1, EP4.2, EP4.3 |
Demonstrate that if a key component of the fire safety system fails, the design is sufficiently robust that a disproportionate spread of fire does not occur (e.g. ASET/ RSET for the remaining floors or fire compartments is satisfied); and Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
|
SS Structural Stability and other properties (2.12). [Building does not present risk to other properties in a fire event] |
CP1, CP5 |
Demonstrate that the building does not present an unacceptable risk to other property due to collapse or barrier failure resulting from a fire; and Demonstrate that the level of safety is at least equivalent to the Deemed-to-Satisfy Provisions. |
Undertake analysis of structure and fire safety systems. |
Notes to Table 1.1 :
Performance Requirement | Design scenarios |
---|---|
CP1 | BE, UT, CS, FI, UF, CF, RC, SS |
CP2 | BE, UT, CS, SF, HS, IS, FI, CF, RC, UF, VS |
CP3 | BE, UT, CS, SF, CF, RC |
CP4 | IS, VS |
CP5 | FI, SS |
CP6 | CS |
CP7 | FI, VS |
CP8 | BE, UT, CS, SF, CF, RC, VS |
CP9 | FI, UF |
DP4 | BE, UT, CS, SF, IS, CF, RC |
DP5 | BE, UT, CS, SF, IS, FI, CF, RC |
DP6 | BE, CS, SF, IS, CF, RC |
DP7 | BE, RC |
EP1.1 | SF, IS, CF, RC |
EP1.2 | SF, CF, RC |
EP1.3 | SF, FI, CF, RC |
EP1.4 | BE, UT, CS, SF, IS, CF, RC |
EP1.6 | FI |
EP2.1 | BE, UT, CS, SF, IS, CF, RC |
EP2.2 | BE, UT, CS, SF, IS, FI, CF, RC, VS |
EP3.2 | FI |
EP4.1 | BE, UT, CS, SF, IS, CF, RC |
EP4.2 | BE, UT, CS, SF, IS, CF, RC |
EP4.3 | BE, UT, CS, SF, IS, CF, RC |