Part 3.2.0 Application

Part 3.2.0 Application

Acceptable Construction Manuals

3.2.0 Application

Performance RequirementsP2.1.1 and P2.2.3 are satisfied for footings and slabs if they are installed in accordance with one of the following:

(a)

The footing or slab is constructed in accordance with AS 2870.

(b)

Piled footings are designed in accordance with AS 2159.

Explanatory information:

Explanatory information:

Composite construction — design requirements for other materials that may be used in combination with the above footing systems, including the use of heavy steel support beams, etc. are described in Part 3.0 — structural provisions.

State and Territory Variations

State and Territory Variations

In New South Wales delete 3.2.0(a) and insert NSW 3.2.0(a) as follows:

(a) The footing or slab is constructed in accordance with AS 2870 except that for the purposes of Clause 5.3.3.1 of AS 2870 a damp-proofing membrane is required to be provided.