Part F2 On-Site Liquid Trade Waste Systems (Deemed-to-Satisfy)

Part F2 On-Site Liquid Trade Waste Systems (Deemed-to-Satisfy)

F2.1 Deemed-to-Satisfy Provisions

Performance Requirements to FP2.4 are satisfied by complying with F2.2.

F2.2 General requirements

(a)

Where pre-treatment facilities are required, they must comply with the requirements of the authority having jurisdiction, including the receiving Network Utility Operator (where relevant) and those responsible for occupational health and safety, dangerous goods management and environmental protection.

(b)

Where the written agreement of the authority having jurisdiction and the receiving Network Utility Operator is required, the liquid trade waste systems and pre-treatment facilities are to comply with the requirements of the authority having jurisdiction and the receiving Network Utility Operator.

Tas F2.2(c)

(c)

Where pre-treatment facilities are not required by the authority having jurisdiction or the receiving Network Utility Operator, the minimum requirement for FP2.3 and FP2.4 is compliance with AS/NZS 3500.2.

Tas F2.2(d), (e)

Explanatory information: Cross-volume considerations

Explanatory information: Cross-volume considerations

Part B1 of NCC Volume One sets out requirements relevant to the excavation of pipework adjacent to a building and footings for the purposes of installing liquid trade waste systems in Class 2 to 9 buildings.