NCC 2016 Volume Three
Classification
Building class 1a Building class 1b Building class 2 Building class 3 Building class 4 Building class 5 Building class 6 Building class 7a Building class 7b Building class 8 Building class 9a Building class 9b Building class 9c Building class 10a Building class 10b Building class 10c

Filter

Classification
Building class 1a Building class 1b Building class 2 Building class 3 Building class 4 Building class 5 Building class 6 Building class 7a Building class 7b Building class 8 Building class 9a Building class 9b Building class 9c Building class 10a Building class 10b Building class 10c
Part F1 On-Site Wastewater Management Systems (Deemed-to-Satisfy)

Part F1 On-Site Wastewater Management Systems (Deemed-to-Satisfy)

F1.1 Deemed-to-Satisfy Provisions

Performance RequirementsFP1.1 to FP1.5 are satisfied by complying with F1.2.

F1.2 General requirements

(a)

The size determination, design and installation of septic tanks must be in accordance with AS/NZS 1546.1.

(b)

The size determination, design and installation of waterless composting toilets must be in accordance with AS/NZS 1546.2.

(c)

The size determination, design and installation of aerated wastewater treatment systems must be in accordance with AS/NZS 1546.3.

(d)

The design, construction, installation, replacement, repair, alteration and maintenance of all sanitary plumbing and drainage systems must be in accordance with—

(i)

AS/NZS 3500.2; or

(ii)

for a Class 1a or Class 10 building only, Section 4 of AS/NZS 3500.5;

and the requirements of this Part.

(e)

The size determination, design, construction, installation, replacement, repair, alteration and maintenance of domestic land application systems must be in accordance with AS/NZS 1547.

(f)

The management of domestic on-site wastewater management systemsand domestic land application systems must be in accordance with AS/NZS 1547.

Tas F1.2(g), (h)

Explanatory information: Cross-volume considerations

Explanatory information: Cross-volume considerations

NCC Volumes One and Two deal with a number of areas of on-site construction which are relevant to on-site wastewater management systems . These include, but may not be limited to, the following:

NCC Volume One Class 2 to 9 buildings

NCC Volume Two Class 1 and 10 buildings

Excavations for pipework adjacent to a building and footings

B1 Structural Provisions

3.1.1 Earthworks