NCC 2019 Volume Three
Classification
Building class 1a Building class 1b Building class 2 Building class 3 Building class 4 Building class 5 Building class 6 Building class 7a Building class 7b Building class 8 Building class 9a Building class 9b Building class 9c Building class 10a Building class 10b Building class 10c

Filter

Classification
Building class 1a Building class 1b Building class 2 Building class 3 Building class 4 Building class 5 Building class 6 Building class 7a Building class 7b Building class 8 Building class 9a Building class 9b Building class 9c Building class 10a Building class 10b Building class 10c
Section B Water services

Section B Water services

Part B2 Heated water services

Performance Requirements

Delete BP2.6(3) and insert NT BP2.6(3) as follows:

NT BP2.6 Energy use and source

(3)

* * * * *

Verification Methods

Delete BV2.1 and insert NT BV2.1 as follows:

NT BV2.1 * * * * *

Explanatory information

This clause has deliberately been left blank.

Deemed-to-Satisfy Provisions

Delete B2.2 and insert NT B2.2 as follows:

NT B2.2 * * * * *

Explanatory information

This clause has deliberately been left blank.

Delete B2.9(1) and insert NTB2.9(1) as follows:

NT B2.9 General requirements

(1)

The design, construction, installation, replacement, repair, alteration and maintenance of a heated water service must be in accordance with AS/NZS 3500.4 with the following concession to clause 5.9.4(a) for existing dwellings

(a)

Where a replacement solar water heater is being fitted and the cold water isolating valve is already fitted on the roof to service the original water heater, this valve can form part of the new solar water heater installation and remain on the roof without being re-located as per clause 5.9.4(a).

Part B4 Fire-fighting water services

Part B4 does not apply in the Northern Territory.